Sacramento River flood-control project

Location: Sacramento Valley, Chico Landing to Collinsville.

Description of plan of improvement: The completion of the entire existing authorized project including the reconstruction, to revised grade and section, of levees on both banks of Sacramento River throughout the valley; west levee of Sutter bypass; and levees of Yolo bypass, Feather River, American River, Cache Creek, and Putah Creek.

Federal authorization: Acts of Congress, March 1, 1917, May 15, 1928, August 26, 1937, and August 18, 1941.

State authorization: Acts of legislature, Statutes of 1911, 1913, 1915, 1925, and Chapter 1514, Statutes of 1945.

Estimated first cost: When the project is completed, exclusive of proposed reservoirs, it is estimated that total expenditures will amount to $110,000,000, including $40,850,000 by the United States, and the remainder by State and local agencies. Need for project: Protection of highly developed agricultural areas, cities and towns, and lines of transportation and communication throughout the Sacramento Valley and Delta.

Status of project: About 82 percent complete.

Appropriation requested and proposed use thereof is as follows:

[blocks in formation]

Bank protection, Red Bluff, southerly-

Clearing obstructions in bypass and overflow channels..

Construction new levees__.

Bank protection and levee set-backs_.

Maintenance dredging, mouth Sacramento River to mile 14.

Total____

Terminus Reservoir

$87,000

50,000

263,000

1,600,000

350,000

150,000

2,500,000

Location: Kaweah River, Tulare County.

Proposed improvement: Dam northeast of Visalia with reservoir having capacity of 100,000 acre-feet for flood control and conservation.

Federal authorization: Public Law No. 534, Seventy-eighth Congress, second session.

State authorization: Chapter 1514, Statutes of 1945.
Estimated first cots: $9,100,000 (1947 prices).

Need for project: Flood protection to city of Visalia and highly productive agricultural lands.

Status of project: Definite project report is about 30 percent complete. Appropriation requested and proposed use thereof: The sum of $950,000 is requested for the 1949 fiscal year for the first year's construction.

Success Reservoir

Location: Tule River, Tulare County.

Proposed improvement: Dam east of Porterville with reservoir having capacity of 50,000 acre-feet for flood control and conservation.

Federal authorization: Public Law No. 534, Seventy-eighth Congress, second session.

State authorization: Chapter 1514, Statutes of 1945.

Estimated first cost: $6,964,000 (1947 prices).

Need for project: Flood protection to city of Porterville and highly productive agricultural lands.

Status of project: Definite project report is about 30-percent complete. Appropriation requested and proposed use thereof: The sum of $950,000 is requested for the 1949 fiscal year for the first year's construction.

Cherry Valley Reservoir

Location: On Cherry Creek in upper Tuolumne River basin, Tuolumne County. Proposed improvement: Dam and reservoir having capacity of 264,000 acrefeet to be constructed by the Modesto-Turlock irrigation districts and the city of San Francisco.

Federal authorization: Public Law No. 534, Seventy-eighth Congress, second

session.

State authorization: Chapter 1514, Statutes of 1945.
Estimated first cost: $6,200,000 (1947 prices).

Need for project: Control of floods on the lower San Joaquin River.

Status of project: Joint studies by Corps of Engineers, Modesto-Turlock irrigation districts, and city of San Francisco to determine Federal share of cost of project are about 50 percent completed.

Appropriation requested and proposed use thereof: The sum of $1,200,000 is requested for the 1949 fiscal year.

San Joaquin River levees

Location: San Joaquin, Stanislaus, and Merced Counties.

Description: Levee construction on San Joaquin River below mouth of Merced River, along the lower portion of Tuolumne and Stanislaus Rivers and through the upper delta.

Federal authorization: Public Law No. 534, Seventy-eighth Congress, second session.

State authorization: Chapter 1514, Statutes of 1945.
Estimated first cost: $3,881,000 (1947 prices).

Need for project: Protection of more than 100,000 acres of highly developed productive agricultural lands and improvements thereon.

Status of project: Definite project report about 2 percent complete.

Appropriation requested and proposed use thereof: $1,000,000 for use during the 1948 fiscal year, for completion of levees along both banks of San Joaquin River, between Mossdale and the mouth of Stanislaus River.

Mr. HYATT. That covers my statement on the whole subject. However, there are some three or four smaller projects which are not represented here today. At the request of our chairman and at the request of the localities' representatives; also I will present them very briefly. The first one is the Pajaro River project, which is in Congressman Anderson's district, between San Jose and Monterey. It is in the budget, more than half completed and needs $185,000 for completion. We requested that amount. I do not think anything further is needed in that situation. It is endorsed in the budget.

With respect to the Salinas River, which is in that same territory, in Congressman Anderson's district, there is a very serious bank erosion along the river. The situation has been investigated by the Corps of Engineers for many years and a project has been worked out at a cost of $3,000,000. We are requesting $1,000,000 for that project. It is not in the budget at the present time.

The third project, the Ventura project, is in the budget for $960,000. That is enough money to complete it. The Board requested $1,000,000 for that project, not knowing of the budget figure. I imagine the $960,000 figure will be satisfactory, because that is what the corps says is needed.

The fourth item is the Prado Dam in Orange County, which needs $263,000. This dam was completed several years ago and in operation, but there was a road relocation involved. There was a suit in court and an agreement with the State and the county under which the United States agreed to assume additional costs of $263,000. That is in the budget, and I think no further comment on it is needed.

I thank the committee for its courtesy and consideration.

Mr. ENGEL. We thank you, sir. Are there any persons opposed to these projects?

Mr. DRAIS. Mr. Chairman, I should like to make a short statement. Mr. ENGEL. We should be glad to hear you.

SATURDAY, JANUARY 24, 1948.

FARMINGTON, CALIF., PROJECT

STATEMENT OF LELAND DRAIS, STOCKTON, CALIF.

Mr. DRAIS. Honorable members of the House Appropriations Committee, gentlemen, my name is Leland Drais, a resident of Stockton, Calif. I represent approximately 100 landowners along Little John Creek, east of Stockton, who will be affected by the construction of a flood-control dam on Little John Creek above the town of Farmington, Calif. As the appropriation bill now stands, it provides solely for flood control. We do not oppose, and will not oppose, the appropriation of any moneys designed to control the floodwaters of Little John Creek, providing flood control is tied in with water conservation and storage. One of the most serious problems confronting the citizens of at least that part of the State of California engaged in farming and agricultural pursuits is the diminishing of water levels throughout the area. This problem has become so serious as to jeopardize the very existence of farming and agricultural pursuits and substantial investments of capital based on those pursuits. The problem cannot be overcome by the sinking of wells, because the water levels in numerous areas have sunken beyond all reasonable and accessible depths. Consequently, we believe, and we respectfully represent, that this appropriation bill should contain the proviso and should be made contingent upon the use of moneys provided for therein for the purpose of establishing a series of small dams running up into the hills toward the water supply of Little John Creek, thus providing for gradual seepage and percolation of waters beneath the surface so as to feed and build up lower water levels. One large dam, we believe, will not accomplish this threefold purpose. A series of smaller dams will not cost substantially more than the appropriation calls for and will not only meet the needs of flood control and will likewise accomplish the crying and serious need of water conservation and storage. We therefore respect fully request that any appropriation made be earmarked for use accordingly.

Several weeks ago in Sacramento, I talked to the United States Bureau of Reclamation. They gave me a map showing the construction of Folsom Dam, and they said at that time, with respect to the Folsom Dam, that they have proposed a canal down the west side of the Sierra Nevada Mountains. We do not know what is ahead of us on this Central Valley water project, but we do believe that the floodwaters will be taken south in this canal. But we did not want another pink elephant on our hands. We feel that if this Farmington Dam is constructed in that area, it will be just a waste of money. It will be a pink elephant, as the Hogan Dam is today. The Hogan Dam has done a wonderful job as far as flood control is concerned; but for conservation and storage, the people there feel that in the next few weeks there will have to be a study of the water conditions there. Just before I left Stockton, the chairman of the water resources board of Calaveras County Chamber of Commerce called me and asked me to go all out at this time and try my best to kill the appro

priation on this Farmington Dam until such time as they make a restudy of their water conditions in Calaveras County. The State water resources board at this time is making a study in Calaveras County; and therefore I respectfully recommend to your honorable committee that if you can kill this appropriation at this time, we should approve it, because we need more time to make a study of what that can do to us.

SATURDAY, JANUARY 24, 1948.

CALIFORNIA FLOOD-CONTROL PROGRAM

STATEMENT OF HON. LEROY JOHNSON, A REPRESENTATIVE IN CONGRESS FROM THE STATE OF CALIFORNIA

Mr. JOHNSON. Mr. Chairman, I represent the Third District of California; and, as the chairman knows, I appreciate your kindness and courtesy in having listened to me at various times. I should like to say that I am heartily in accord with the statements made by all of the proponents of these projects from California. I have never heard a group of witnesses who presented their case in better fashion and more to the point.

With reference to the Farmington Reservoir, I might say to my friend, Mr. Drais, that if he wants conservation of water, this is one of the steps which will give him conservation of water. The Hogan Dam to which he referred is something I am thoroughly familiar with. I spent 83 days in court involved in the problems of that dam.

It is a success as a flood-control dam, and some day it will be enlarged so as to make a combined flood-control and conservation dam. In that manner the water from this dam, which will be badly needed in the future, will be available for agricultural and domestic use.

I ask, Mr. Chairman, that I may be permitted to extend my remarks in the record at such length as seems desirable.

Mr. ENGEL. Without objection, the gentleman is granted that per

mission.

[blocks in formation]

Mr. JOHNSON. Are you going to hear river and harbor projects? Mr. ENGEL. When we have finished with these folks, we will have rivers and harbors projects briefly.

Mr. JOHNSON. Thank you.

SATURDAY, JANUARY 24, 1948.

HOGAN DAM AND FARMINGTON DAM

STATEMENT OF WALTER B. HOGAN, CITY MANAGER OF THE CITY OF STOCKTON, CALIF.

Mr. ENGEL. Have you anything further, Mr. Miller?

Mr. MILLER. Mr. Chairman, may I request a minute and a half on the Hogan Dam and also the Farmington Dam to rebutt what has been

presented?

I would like to say this, if I may: The State water resources board has investigated the Farmington Dam very thoroughly. The Army engineers have investigated it. I think there are over 16 sites in that area above the dam. The State engineer has reported on this dam. It is a flood-control dam and not a storage reservoir for water. I would like to ask that Mr. Hogan be permitted a minute and a half on this matter.

Mr. ENGEL. We shall be glad to hear Mr. Hogan.

Mr. HOGAN. Mr. Chairman and gentlemen, in connection with the Farmington Dam, with respect to the irrigation feature, there was considerable opposition to irrigation in this area, and that is a situation I have had to meet for the past year or year and a half. There is a certain group that want irrigation. The city of Stockton as such is not concerned whether they have irrigation or not. We want flood control. With respect to irrigation, I would like to read into the record a letter addressed to Lt. Gen. Raymond A. Wheeler, Chief of Engineers, written by Wesley R. Nelson, Acting Commissioner, Bureau of Reclamation, dated December 17, 1947. It is as follows:

Lt. Gen. RAYMOND A. WHEELER,

DEPARTMENT OF THE INTERIOR,

BUREAU OF RECLAMATION, Washington 25, D. C., December 17, 1947.

Chief of Engineers, Department of the Army.

MY DEAR GENERAL WHEELER: In your letter of November 7, 1947, you stated that the Corps of Engineers is now preparing its definite project report on the Farmington Reservoir project on Littlejohn Creek in California, which was authorized by the Flood Control Act of 1944. You requested our concurrence in the present plans of the Corps of Engineers to construct the Farmington Dam and Reservoir for flood control only to a capacity of about 52,000 acre-feet, without specific provisions for future raising of the dam.

As explained in your letter, Farmington Reservoir was authorized for construction to a capacity of 100,000 acre-feet on the basis of the proposal of the Bureau of Reclamation that additional storage be provided in the reservoir for conservation purposes. You are correct in your statement that we believe irrigation storage on Littlejohn Creek may be desired ultimately, but that the need for such storage is too far in the future to warrant provision therefor in the initial construction. Accordingly, we have no objection to the construction of Farmington Reservoir for flood control only, without specific provisions for future raising of the dam as presently planned by the Corps of Engineers.

Sincerely yours,

WESLEY R. NELSON, Acting Commissioner.

Mr. Chairman, I would like to file also in rebuttal this statement which I prepared in anticipation of the opposition.

Mr. ENGEL. Without objection, it may be received in the record. (The statement referred to is as follows:)

STATEMENT OF W. B. HOGAN, CITY MANAGER OF THE CITY OF STOCKTON, CALIF., IN REBUTTAL BEFORE THE SUBCOMMITTEE (WAR DEPARTMENT, CIVIL FUNCTIONS) OF THE APPROPRIATIONS COMMITTEE CONCERNING OBJECTIONS WHICH HAVE BEEN VOICED TO THE CONSTRUCTION OF A DAM ACROSS LITTLEJOHN CREEK, CALIF.

Shortly after the Farmington Dam project was approved by Congress, under Public Law 534, Seventy-eighth Congress, second session, considerable opposition developed from landowners, both above and below the dam. This opposition was based primarily on three factors, viz:

1. Unwillingness of owners in reservoir basin to sell their lands or give flowage rights thereon;

2. Fear of being placed in an irrigation district; and