" ... due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, acts... "
Cases Decided in the Court of Claims of the United States - Strana 401
autor/autoři: United States. Court of Claims - 1946
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the Court of Claims of the United States, Svazek 111

United States. Court of Claims - 1948 - 886 str.
...operation of any Governmental preferences, priorities or allocations of equipment or material) , acts of another Contractor in the performance of a contract...quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or material suppliers due to such causes (unless...
Úplné zobrazení - Podrobnosti o knize

Decisions of the Comptroller General of the United States, Svazek 23

United States. General Accounting Office - 1944 - 1220 str.
...These it describes as "including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather, or delays of subcontractors due to such causes." The purpose of the proviso to protect the contractor against the unexpected, and its grammatical sense...
Úplné zobrazení - Podrobnosti o knize

The Law of Government Contracts

Robert Preston Shealey - 1927 - 600 str.
...beyond the control of and without the fault or negligence of the contractor, and including acts of God, quarantine restrictions, strikes, freight embargoes,...unusually severe weather or delays of subcontractors, within which to apply in writing to the contracting officer for extension of time for completing the...
Úplné zobrazení - Podrobnosti o knize

Hearings Before the Committee on the Judiciary, House of Representatives ...

United States. Congress. House. Committee on the Judiciary - 1928 - 900 str.
...negligence of the contractor, including, but not restricted, to, acts of God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes." For the entire provision relating to delays and damages see section 9 of Standard Form No. 23. The...
Úplné zobrazení - Podrobnosti o knize

Treasury Department Appropriation Bill for 1929: Hearing Before the ...

United States. Congress. House. Committee on Appropriations - 1928 - 970 str.
...of the contractor, including, "but not restricted to. acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes: Provided, That the contractor shall within ten days from the beginning of any such delay notify the...
Úplné zobrazení - Podrobnosti o knize

To Establish Uniform Requirements for Government Contracts: Hearing Before ...

United States. Congress. House. Committee on the Judiciary - 1928 - 228 str.
...negligence of the contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine...embargoes, and unusually severe weather, or delays of the subcontractors due to such causes." This provision is made known to all bidders and it is assumed,...
Úplné zobrazení - Podrobnosti o knize

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 str.
...negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within ten days from the beginning of any such delay notify...
Úplné zobrazení - Podrobnosti o knize

Decisions of the Comptroller General of the United States, Svazek 9

United States. General Accounting Office - 1930 - 608 str.
...negligence of the contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine...strikes, freight embargoes, and unusually severe weather, but not including delays caused by subcontractors: Provided furthei; That the contractor shall, within...
Úplné zobrazení - Podrobnosti o knize

To Establish Uniform Requirements for Government Contracts: Hearing Before ...

United States. Congress. House. Committee on the Judiciary - 1930 - 180 str.
...unforeseeable causes including but not restricted to acts of God, acts of the Government, or the public enemy, fires, floods, epidemics, quarantine restrictions,...strikes, freight embargoes, and unusually severe weather "but not including delays caused by subcontractors" force the Government to purchase needed envelopes...
Úplné zobrazení - Podrobnosti o knize

The Construction of Hoover Dam: Preliminary Investigations, Design of Dam ...

United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 str.
...negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within ten days from the beginning of any such delay notify...
Úplné zobrazení - Podrobnosti o knize