" ... shall ascertain the facts and the extent of the delay and extend the time for completing the work when in his judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto... "
Cases Decided in the Court of Claims of the United States - Strana 396
autor/autoři: United States. Court of Claims - 1948
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the United States Court of Claims ... with ..., Svazek 121

United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 str.
...contractor shall within 10 days from the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain...such an extension, and his findings of facts thereon snail be final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the United States Court of Claims ... with ..., Svazek 147

United States. Court of Claims, Audrey Bernhardt - 1962 - 712 str.
...period of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the Court of Claims of the United States, Svazek 107

United States. Court of Claims - 1947 - 806 str.
...Case of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the United States Court of Claims ... with ..., Svazek 145

United States. Court of Claims, Audrey Bernhardt - 1959 - 820 str.
...settlement of the contract) notify the contracting officer in writing of the 145 C. Cte. Findings of Fact causes of delay, who shall ascertain the facts and...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the Court of Claims of the United States, Svazek 94

United States. Court of Claims - 1942 - 818 str.
...notify the contracting officer in writing of the causes 04 C. CIS. Reporter's Statement of the Case of delay, who shall ascertain the facts and the extent...fact justify such an extension, and his findings of fact shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days, by...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the United States Court of Claims ... with ..., Svazek 114

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 str.
...period of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...his judgment the findings of fact justify such an extensionj and his findings of fact thereon shall be final and conclusive on the parties hereto, subject...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the United States Court of Claims ... with ..., Svazek 122

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 str.
...Contract) notify the Contracting Officer in writing of the causes of delay, 122 C. Gig. Finding! of Fact who shall ascertain the facts and the extent of the...fact justify such an extension, and his findings of fact thereon snail be final and conclusive on the parties hereto, subject only to appeal, within 30...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the United States Court of Claims ... with ..., Svazky 120–130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 str.
...and unusually severe weather or delays of subcontractors due to such causes. The contracting officer shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within thirty...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the Court of Claims of the United States, Svazek 104

United States. Court of Claims - 1946 - 936 str.
...contract) notify the contracting officer in writing of the causes 01 delay, who shall ascertain the fact and the extent of the delay and extend the time for...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Úplné zobrazení - Podrobnosti o knize

Cases Decided in the Court of Claims of the United States, Svazek 105

United States. Court of Claims - 1946 - 920 str.
...because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts and the extent of the delay...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application...